Glennies Creek Bridge Renewal
ARTC’s FY19 Annual Works Plan (AWP) includes a structures component for the replacement of stringers on the Glennies Creek Underbridge at 252.610km along the Main Northern Railway in the Hunter Valley. The bridge is a 4 span transom top steel bridge with timber transoms fixed to steel stringers.
Further to this, re-railing of the Up Main was required from 252.785km to 253.180km.
The Intent of the project is to improve the existing track reliability and stability at and surrounding Glennies Creek. This includes the replacement of old for new steel stringers, bracing and timber transoms over three (3) financial years, track formation reconditioning and re-railing. Works are to commence on the Up Main, including re-railing works, before commencing on the Down Main.
Bridge and Civil were initially engaged by ARTC to complete the fabrication, removal and replacement of 42 stringers and associated bracing and timber transoms on the Up Main. Once works had begun, ARTC engaged Bridge and Civil to complete the fabrication and replacement of the remaining 14 stringers and associated bracing and timber transoms on the Up Main.
Bridge and Civil were able to successfully complete the entire scope of works over 4 ARTC Scheduled Possessions.
Further to this, re-railing of the Up Main was required from 252.785km to 253.180km.
The Intent of the project is to improve the existing track reliability and stability at and surrounding Glennies Creek. This includes the replacement of old for new steel stringers, bracing and timber transoms over three (3) financial years, track formation reconditioning and re-railing. Works are to commence on the Up Main, including re-railing works, before commencing on the Down Main.
Bridge and Civil were initially engaged by ARTC to complete the fabrication, removal and replacement of 42 stringers and associated bracing and timber transoms on the Up Main. Once works had begun, ARTC engaged Bridge and Civil to complete the fabrication and replacement of the remaining 14 stringers and associated bracing and timber transoms on the Up Main.
Bridge and Civil were able to successfully complete the entire scope of works over 4 ARTC Scheduled Possessions.
Client
Australian Rail Track Coorporation
Location
Glennies Creek, NSW
Project
Snapshot of the work that took place over the available 292hrs
• 535m Re-railing completed
• 308 transoms replaced old for new
• 116 tonnes of existing steel stringers removed
• 128 stub connections installed
• 210 tonnes new steel stringers Installed
• 2800 existing rivets removed
• 4900 bolts Installed
• 9800 washers Installed
• 9800 nuts Installed
• 234 crane lifts
• 28 bays completed
• 616 Delkor plates Installed
• 1848 screw spikes installed
• 616 huck Bolts Installed
Available Closedowns:
September 18 (62hr)
November 18 (96hr)
February 19 (72hr)
April 19 (62hr)
• 535m Re-railing completed
• 308 transoms replaced old for new
• 116 tonnes of existing steel stringers removed
• 128 stub connections installed
• 210 tonnes new steel stringers Installed
• 2800 existing rivets removed
• 4900 bolts Installed
• 9800 washers Installed
• 9800 nuts Installed
• 234 crane lifts
• 28 bays completed
• 616 Delkor plates Installed
• 1848 screw spikes installed
• 616 huck Bolts Installed
Available Closedowns:
September 18 (62hr)
November 18 (96hr)
February 19 (72hr)
April 19 (62hr)